a ,b,c can do a work in 6,8,10 days a works for 2 days. b&c for 2
a ,b,c can do a work in 6,8,10 days a works for 2 days. b&c for 2 days,remaining work completed by c. In how many days work is completed?
|
|
|
|
|
|
#2 (permalink) |
|
Junior Member
Join Date: Nov 2008
Age: 24
Posts: 5
Thanks: 0 Thanked 0 Times in 0 Posts Thanks: 0
Thanked 0 Times in 0 Posts
Rep Power: 1
|
Re: a ,b,c can do a work in 6,8,10 days a works for 2 days. b&c for 2
A's 2 days work=2/6=1/3;
B & c 2 day work=2(1/8+1/10)=9/20; Total work done by A,B,C in 4 days=1/3+9/20=4/5; Remaining work=1-4/5=1/5; C does 1/10 of work in 1 day C does 1/5 of work in x days x=2; Total days taken by c to finish remaining work=2; Total number of days taken by A,B,C to finish work=2+2+2=6 Days ![]() |
|
|
|
![]() |
| Currently Active Users Viewing This Thread: 1 (0 members and 1 guests) | |
| Thread Tools | |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Walk Ins @ Wipro Technologies | sridhar | Walk-ins | 14 | 03-09-07 03:52 PM |
| A man, a woman, and a child can do a piece of work in 6 days. man only | m.gayatri | Aptitude Questions | 0 | 25-01-07 12:06 PM |
| Anand finishes a work in 7 days, Bittu finishes the same | m.gayatri | Aptitude Questions | 0 | 25-01-07 11:08 AM |
| nobel prize | AjayKumar.Kataram | Inspire yourself & Others - Leaders Zone | 1 | 22-09-06 01:47 PM |
| Aptitude contest - 55 | HELP | Aptitude Questions | 8 | 04-05-06 07:24 AM |