Q) Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men work to complete the job?ans:71/2hrs.
can anyone reply for this question with complete solution if they know.plz it's urgent. Last edited by sirisha999; 25-10-06 at 05:07 PM. Reason: to add few words |
|
|
|
|
|
#2 (permalink) |
|
Junior Member
Join Date: Jan 2007
Age: 23
Posts: 18
Thanks: 5 Thanked 1 Times in 1 Posts Thanks: 5
Thanked 1 Time in 1 Post
Rep Power: 2
|
Re: aptitude questions
I think ur ans is wrong. It may be 6hrs45mins...
__________________
Warm Regards, GaneshSundar.R (0) 99424 22122
|
|
|
|
![]() |
| Currently Active Users Viewing This Thread: 1 (0 members and 1 guests) | |
| Thread Tools | |
| Display Modes | Rate This Thread |
|
|
Similar Threads
|
||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| tips for interview | ozobalu | HR Questions | 9 | 23-09-08 12:32 AM |
| Dug it | yathish | Companies Info & Recruitment Process | 4 | 10-09-08 06:25 PM |
| must read all UG students!!!!!!!!!!!!! | sanjay | Other Queries | 15 | 04-09-08 04:10 PM |